The final payment should be released against a checklist, not a feeling. Work through this list room by room — most of these checks take under a minute each.
Bathrooms
- Waterproofing test. Flood the shower area for 24–48 hours and check the ceiling below for damp patches.
- Falls to the drain. Pour water at the far corner — it should reach the drain without pooling anywhere.
- Grout lines. Consistent width, no hollow-sounding tiles when tapped.
- Cistern and flush. Flush three times in a row; check for seepage at the base.
- Hot and cold. Confirm both lines actually deliver at the fittings you will use.
- Exhaust fan. Runs, vents outside, and is not wired into the light circuit by mistake.
- Mirrors and fittings. Level, firmly anchored, silicone sealed at edges.
Kitchen
- Sink plumbing. Fill the sink, release, and inspect the trap underneath for drips.
- Dishwasher point. Isolated valve, dedicated electrical point, and a drain connection you can actually reach?
- Chimney or hood. Ducted outside, not recirculating, unless that was the design.
- Countertop joints. Tight, level, and silicone sealed at the wall upstand.
- Cabinet hardware. Every door aligned, every soft-close hinge working.
- Under-cabinet lighting. On a separate switch, positioned where you will actually chop.
Across both rooms
- Silicone everywhere wet meets solid — no gaps behind the WC, under the vanity or at the shower screen.
- Tile-to-skrirting junction sealed, not just butted.
- Water pressure test at the highest fixture in the house, not just the ground floor.
- Isolation valves labelled — you should be able to shut one bathroom without killing the house.
The documentation you should receive
Before releasing the final payment, collect:
- Warranty cards for sanitaryware, appliances and water heaters
- As-built drawings showing where pipes and conduits run in the walls
- Paint and material codes for future touch-ups
- Signed snag sheet confirming every item above is closed
A handover without documentation is a handover that will cost you later — the first time someone drills into a concealed pipe, you will wish you had the as-built drawing.
Print this list, walk the house with your site engineer, and tick every line before the last cheque clears.
Latest insights
· 2 min read
10 Design Ideas for Narrow Plots That Feel Spacious
Proven layout, light and material strategies for 3-marla and 5-marla plots — from double-height voids to continuous sightlines.
Read article· 2 min read
Grey Structure Construction Cost in Pakistan (2026 Rate Guide)
A practical breakdown of grey structure rates per sq. ft. in Lahore, Islamabad, Faisalabad, Multan and Sialkot — and what actually moves your number up or down.
Read article· 2 min read
Turnkey vs Grey Structure: Which Is Right for Your Build?
Both routes build the same house — but they ask very different things of you. Here is how to choose between grey structure and turnkey construction.
Read articleReady to talk about your own build?
Send your plot details and requirements — you will get a cost range and a call back within 24 hours.
Get a free quote